RERA forensic audit during CIRP
Case BriefsTribunals/Commissions/Regulatory Bodies

With expenditure claimed at 75—77% of project cost against actual physical progress of only 48.13%, the Authority ordered a limited forensic audit of the Avalon Royal Park project, distinguishing the RERA audit from IBC insolvency audit provisions and holding that the two frameworks can operate harmoniously without conflict.

Tree Felling by DLF
Case BriefsHigh Courts

“Since none of the khasra numbers in regard to which DLF has been granted permission to fell trees, fall within the Aravalli Hills area, this Court does not deem it appropriate to proceed in the matter especially when DLF was granted permission to fell trees vide different orders after following due process of law.”

Punjab and Haryana High Court
Case BriefsHigh Courts

According to the news report, residents and environmental activists have launched protests and official petitions against the alleged tree felling citing destruction of the Aravallis in DLF Phase 5.

Case BriefsTribunals/Commissions/Regulatory Bodies

Odisha Real Estate Regulatory Authority, Bhubaneswar: Siddhanta Das, Chairperson, Pradeep Kumar Biswal, Member – I and Ramanath Panda, Member – II held