RERA forensic audit during CIRP
Case BriefsTribunals/Commissions/Regulatory Bodies

With expenditure claimed at 75—77% of project cost against actual physical progress of only 48.13%, the Authority ordered a limited forensic audit of the Avalon Royal Park project, distinguishing the RERA audit from IBC insolvency audit provisions and holding that the two frameworks can operate harmoniously without conflict.

National Company Law Tribunal
Case BriefsTribunals/Commissions/Regulatory Bodies

The NCLT held that non-delivery of possession despite payments and continued acknowledgment of liability through emails and communications proved default under Section 7 IBC.