Introduction
Law Day is observed on 26 November to mark the adoption of the Constitution in 1949. Commercial law is seldom a part of the discussion on the day. Yet for a supplier waiting for payment, a contractor whose bills are withheld or a company holding an award it cannot enforce, the Rule of Law is measured in practical terms: whether the bargain will be honoured, whether the chosen forum will decide the dispute within a reasonable time, and whether the decision, once rendered, will be allowed to rest.
More than five decades ago, the Supreme Court in E.P. Royappa v. State of T.N.1 observed that “equality and arbitrariness are sworn enemies; one belongs to the Rule of Law in a republic while the other, to the whim and caprice of an absolute monarch”. In commercial disputes, arbitrariness seldom announces itself. It is more often found in uncertainty and delay than in any overt act of discrimination.
In 15 years of practice in commercial, contractual and arbitration law, as counsel and as an arbitrator, I have seen the law in this field move considerably, and mostly in the right direction. The Arbitration and Conciliation Act, 1996 (the 1996 Act) has been amended thrice, the grounds of challenge to awards have been narrowed, and the courts have repeatedly declared a policy of minimal interference. A gap, however, persists between what the law declares and what a litigant actually experiences. It is that gap which this article seeks to examine.
Sanctity of the bargain
The first premise of commercial law is that parties are bound by what they have agreed. A court does not make a better bargain for a party than the one that party made for itself. The Arbitration and Conciliation (Amendment) Act, 2015 (2015 Amendment) carried this principle into arbitration by substituting Section 28(3), which requires the Arbitral Tribunal, in all cases, to take into account the terms of the contract and the trade usages applicable to the transaction.
The principle is easily stated but tested often. Contracts with the State and its instrumentalities are standard form documents drafted entirely by the employer. They routinely contain clauses that bar claims for delay, permit unilateral deductions or make the decision of an officer of the employer final. The contractor signs them on a take it or leave it basis. The Rule of Law requires these clauses to be read as they stand, without favour to either side, and requires the State, which drafted them, to accept their consequences when they operate against it.
The more unsettling challenge to the bargain has, at times, come from the shifting position of law itself. The stamp duty saga is the clearest instance. In January 2021, a three-Judge Bench in N.N. Global Mercantile (P) Ltd. v. Indo Unique Flame Ltd.2 held that non-payment of stamp duty on the underlying contract did not invalidate the arbitration agreement contained in it, the defect being curable. In April 2023, a Constitution Bench, by a majority of 3:2, overruled that view3 and held that an arbitration agreement contained in an unstamped or insufficiently stamped instrument would not be enforceable in law until the instrument was duly stamped, and that the Referral Court was bound to impound such an instrument before acting on it. In December 2023, a seven-Judge Bench overruled the Constitution Bench and held that insufficient stamping renders an instrument inadmissible in evidence, not void, and that the objection is for the Arbitral Tribunal and not the Referral Court to examine.4
Each of these judgments was well reasoned, and the final answer has been widely welcomed, but the journey to it came at a cost. For nearly eight months, a party holding a valid commercial bargain could not have its arbitrator appointed, because a fiscal statute meant to collect revenue was read as a reason to deny the agreed forum. Lawyers advised clients on a position which, as events turned out, was temporary. Predictability of precedent is as much a part of the Rule of Law as its correctness.
Finality of the award
An arbitral award is meant to bring the dispute to an end, subject only to a narrow and supervisory challenge. The 2015 Amendment narrowed the public policy ground under Section 34 and introduced patent illegality as a ground for domestic awards, with the express caveat, in the proviso to Section 34(2-A), that an award “shall not be set aside merely on the ground of an erroneous application of the law or by reappreciation of evidence”. The Supreme Court explained these limits in Associate Builders v. DDA5 and, after the amendment, in Ssangyong Engg. & Construction Co. Ltd. v. NHAI.6
The dispute between Delhi Metro Rail Corporation (DMRC) and Delhi Airport Metro Express Private. Limited (DAMEPL) tested those limits and, with them, the idea of finality. The Arbitral Tribunal rendered its award in May 2017. A Single Judge of the Delhi High Court dismissed DMRC’s challenge under Section 34. The Division Bench, in appeal under Section 37, set aside the award in part. In September 2021, the Supreme Court allowed DAMEPL’s appeal and restored the award7, and DMRC’s review petition was dismissed. In April 2024, a three-Judge Bench allowed DMRC’s curative petition, set aside the 2021 judgment and restored the decision of the Division Bench.8 The award thus fell nearly seven years after it was made, at the fifth tier of judicial scrutiny.
The court itself cautioned that its curative jurisdiction should not be used to open a further stage of challenge against arbitral awards, and justified its intervention on the ground that restoring an award which suffered from patent illegality had caused a grave miscarriage of justice. Whatever view one takes on the merits, a party which succeeds in arbitration in India now knows that its award may pass through Sections 34 and Section 37, a special leave petition, a review petition and, in an exceptional case, a curative petition. Each tier carries a possibility, however remote, of reversal, and that possibility is itself a cost which parties weigh while deciding whether to settle, to enforce or to wait.
The Constitution Bench in Gayatri Balasamy v. ISG Novasoft Technologies Ltd.9 added a further dimension. By a majority of 4:1, it held that courts possess a limited power to modify an award under Sections 34 and 37, such as by severing the invalid portion, correcting clerical or computational errors, or modifying post-award interest, and that the Supreme Court may also exercise its power under Article 142 of the Constitution, though with great caution. Justice K.V. Viswanathan dissented, holding that the 1996 Act confers no power to modify an award. The difficulty is that Article 142 is not confined by the limits of Section 34, while the Rule of Law in arbitration depends upon the parties knowing in advance the scope of the review their award will face.
Delay as a denial of the Rule of Law
Delay is perhaps the most pervasive threat, and I have written earlier on its incidence at the pre-appointment stage, during the proceedings and after the award.10 Section 29-A, as amended in 2019, requires an award in a domestic arbitration within 12 months from the completion of pleadings, extendable by six months with the consent of the parties, and thereafter only by the court. Section 34(6) requires a challenge to be disposed of within one year from the service of notice. The Supreme Court has, however, held that the latter time-limit is directory.11 In practice, challenges under Sections 34 and 37 continue for years.
The 2015 Amendment removed the automatic stay that followed the mere filing of a challenge. In BCCI v. Kochi Cricket (P) Ltd.12 the Supreme Court applied the amended Section 36 to pending challenges, and in Hindustan Construction Co. Ltd. v. Union of India13 it struck down Section 87, which had been inserted in 2019 to revive the old position. An award-holder must nevertheless wait for the court to decide whether to grant a stay, on what terms and against what security. A statutory provision for provisional enforcement of a defined portion of the award, pending the challenge, would go a long way.
In a money claim, delay works in favour of the party in default. It retains the money for years, often at a cost lower than its cost of borrowing, and settles, if at all, at a discount. The losing party thus ends up profiting from the very time taken to decide the dispute.
The State as a contracting party
The State is often described as the largest litigant in the country, and its conduct as a contracting party is not purely private. In Shrilekha Vidyarthi v. State of U.P.14 the Supreme Court held that Article 14 applies to the actions of the State even in the contractual field, and in ABL International Ltd. v. Export Credit Guarantee Corpn. of India Ltd.15 it held that a writ petition is maintainable in a contractual dispute with the State where its action is arbitrary.
These principles have found their sharpest application in blacklisting. In Erusian Equipment & Chemicals Ltd. v. State of W.B.16 the court held that blacklisting deprives a person of the privilege of entering into lawful relationships with the government and cannot be done without a hearing. In Gorkha Security Services v. State (NCT of Delhi)17 it held that the show-cause notice must specify that blacklisting is the action proposed. In Kulja Industries Ltd. v. Western Telecom Project BSNL18 it held that debarment must be proportionate to the default and cannot be for an indefinite period.
The Constitution Bench in Central Organisation for Railway Electrification v. ECI SPIC SMO MCML (JV)19 carried the principle into the arbitration clause itself. It held that a clause which permits one party to appoint the sole arbitrator unilaterally, or to curate a panel from which the other party must choose, offends the principle of equal treatment of parties under Section 18, 1996 Act, and that in public-private contracts such clauses are also violative of Article 14.
The other side of the State’s conduct is its litigation policy. Adverse awards against State instrumentalities are challenged almost as a matter of course, often because no officer wishes to be answerable for accepting one. A litigation policy which requires a reasoned decision at a senior level before an award is challenged would serve the State better than the present practice.
Statutory arbitration under the MSMED Act
Chapter V of the Micro, Small and Medium Enterprises Development Act, 2006 (the MSMED Act) creates a statutory mechanism for the recovery of delayed payments. In Gujarat State Civil Supplies Corpn. Ltd. v. Mahakali Foods (P) Ltd.20 the Supreme Court held that Chapter V overrides the 1996 Act, that the Facilitation Council which conducted the conciliation may itself act as the arbitrator, and that an independent arbitration agreement between the parties cannot oust the jurisdiction under Section 18. Section 19 requires a buyer who challenges an award to deposit 75 per cent of the awarded amount. The design was deliberately weighted in favour of the supplier, and the original Section 18(5) required every reference to be decided within 90 days. However, in practice, this timeline is seldom adhered to.
Parliament has responded with the Micro, Small and Medium Enterprises Development (Amendment) Act, 2026, which received assent on 13 August 2026 and is being brought into force in phases. The amendments prescribe outer limits for each stage of Section 18 proceeding: mediation within 90 days of the first appearance, commencement of arbitration within thirty days of the failure of mediation, and an award within 90 days of the completion of pleadings. They also permit recovery of an award as arrears of land revenue, require the release to the supplier of at least half of the awarded amount where the challenge remains pending for more than six months, and require every Council to include a member from the field of law.
While these changes are welcome, two concerns remain. First, the amended provisions prescribe timelines but no consequence for their breach, and a timeline without a consequence is likely to meet the fate of the original Section 18(5). Second, the law on whether a supplier under a works contract can invoke Section 18 at all is unsettled, and the question is pending before the Supreme Court.21 In my experience of such references, an unsettled threshold question of this kind is exactly what a buyer uses to stall a proceeding, usually by way of a writ petition at an interlocutory stage.
State statutory arbitration tribunals
The most acute concern in my practice arises from the arbitration tribunals created by State legislation for works contracts. In Gujarat, the Gujarat Public Works Contracts Disputes Arbitration Tribunal Act, 1992 (the Gujarat Act) mandates reference of disputes arising out of works contracts of the State Government and notified public undertakings to the Tribunal constituted under it, irrespective of an arbitration clause in the contract. Section 21 provides that on the Gujarat Act becoming applicable to a dispute, the general law of arbitration ceases to apply to it to the extent of inconsistency, and pending arbitration proceedings stand transferred to the Tribunal. In State of Gujarat v. Amber Builders22 the Supreme Court held that the Tribunal can grant interim relief under Section 17, 1996 Act, since the two enactments are not inconsistent on that aspect.
A municipal body assumes the character of a public undertaking under the Gujarat Act only upon a notification in the Official Gazette.23 Notifications of December 2024 and May 2025 have brought municipalities and municipal corporations within the Gujarat Act. The Gujarat High Court in GPC Infrastructure Ltd. v. Gandhinagar Municipal Corpn.24 has since dismissed a batch of petitions under Section 11, 1996 Act and held that, by operation of Section 21, such disputes must go to the Tribunal even where arbitration had been invoked under the contract before the notification. A contractor who signed a contract providing for arbitration under the 1996 Act thus finds the dispute moved to a different forum by an executive notification issued after the contract was made.
Madhya Pradesh presents a similar picture under the Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983. After a difference of opinion in 2012,25 a three-Judge Bench held in 2018 that the State enactment prevails over the 1996 Act in respect of works contracts.26
There is nothing wrong in principle with a specialised forum for public works disputes. The difficulty is that the State enactments have not kept pace with the reforms in the general law. As I have pointed out earlier with reference to the Gujarat Act,27 a large volume of references is handled by one or two Benches, the Act prescribes no outer limit for the award, the proceedings are conducted with the rigours of the Civil Procedure Code, 1908 and the law of evidence, there is no fast track procedure even for simple claims, and the award is subject to a revision before the High Court which permits scrutiny of the findings far beyond the grounds in Section 34. There is also no provision corresponding to Section 36, 1996 Act which effectively requires a deposit of the awarded amount for a stay. The timelines of Section 29-A, the narrowed grounds of challenge and the end of the automatic stay are thus unavailable to the very class of contractors who deal with the largest public employer in the State.
There is a more fundamental concern with these tribunals. Under both enactments, the Chairman and the members of the Tribunal are appointed by the State Government.28 Apart from judicial officers, the Gujarat Act makes eligible persons who have served for three years as a Secretary to the Government of Gujarat or as a Chief Engineer of the State, and the Madhya Pradesh enactment similarly draws upon Chief Engineers of the State’s Public Works, Irrigation and Public Health Engineering Departments. The State or one of its instrumentalities is a party to every reference before these tribunals. The adjudicator is therefore selected by one of the parties to the dispute, and may well be a former officer of the very department whose decisions are under challenge. Under the 1996 Act, the Supreme Court would not permit such an arrangement. In TRF Ltd. v. Energo Engg. Projects Ltd.29 it held that a person who is himself ineligible to act as an arbitrator cannot nominate one. In Perkins Eastman Architects DPC v. HSCC (India) Ltd.30 it held that a party having an interest in the outcome of the dispute cannot unilaterally appoint the sole arbitrator. The Constitution Bench in the case of Central Organisation for Railway Electrification31 took the principle further and held that unilateral appointment offends the equal treatment of parties under Section 18 and, in public-private contracts, Article 14. If the State cannot appoint the arbitrator under a contract, it is difficult to see why it should be able to do so under a statute of its own making. Independence of the adjudicator is an incident of the Rule of Law itself and is not confined to consensual arbitration, and Article 14 binds the legislature as much as the executive. The Supreme Court has repeatedly affirmed the exclusive jurisdiction of these tribunals, but, to my knowledge, the manner of appointment of their members has not yet been examined on the touchstone of the principles laid down in the case of Central Organisation for Railway Electrification. The question deserves an answer.
The vires of the Madhya Pradesh enactment were challenged soon after it came into force. In M.P. Spectro Engg. Corpn. v. State of M.P.32 a Division Bench of the Madhya Pradesh High Court rejected the challenge on every ground. It held that works contracts form a distinct class, that a statutory arbitration does not depend upon consent and falls within Entry 13, List III, and that a revision to the High Court was an adequate remedy. The argument that the State appoints, can remove and fixes the pay of the members, and thereby sits as a Judge in its own cause, was specifically raised and rejected. The court reasoned that a tribunal headed by a High Court Judge, with Senior District Judges as members, is no less independent than the officers of the State who were then commonly named as arbitrators in government contracts. The validity of the enactment was later reaffirmed by a Full Bench of that High Court.33
Spedra Engineering was decided in 1987. The very premise on which the independence argument was answered, namely, that government contracts routinely named the employer’s own officers as arbitrators, has since been rejected by the Supreme Court in TRF34, Perkins Eastman35 and Central Organisation for Railway Electrification36. The law on the independence of tribunals has also travelled a long distance in the interregnum. In the Madras Bar Assn. (6) v. Union of India line of cases, most recently in November 202537, the Supreme Court has held that legislation enabling executive control over the appointment and tenure of Members of Tribunals strikes at judicial independence. In State of Kerala v. James Varghese38 it upheld the invalidation of a Kerala law which sought to revoke arbitration clauses and reopen awards in contracts of the State. In my view, a fresh challenge to the State enactments founded on these later developments would not be foreclosed by a decision rendered nearly four decades ago.
The Rule of Law can accommodate a special forum. It cannot easily accommodate a special forum that is slower and permits a wider challenge than the general one, into which a party is compelled by statute, and in which the State is invariably one of the parties. Either the State enactments must be brought in line with the 1996 Act in respect of the manner of appointment of members, timelines, constitution of Benches, expert members and the scope of challenge, or the compulsion to approach them must be reconsidered.
Conclusion
None of the concerns raised above calls for a radical overhaul. Conflicting views on a basic question, such as the effect of stamping, can be referred to a larger Bench early, before a generation of disputes is decided on a position that may not last. A statutory time-frame for the disposal of challenges under Sections 34 and 37, coupled with provisional enforcement of a part of the award, would reduce the incentive to challenge for the sake of time. A State litigation policy requiring a reasoned decision before an award is challenged would reduce the number of mechanical challenges. The State arbitration tribunal enactments need a fresh look, beginning with the manner in which their members are appointed, so that a contractor dealing with the State is not placed in a worse position than one dealing with a private employer. And the timelines in the MSMED Act need a consequence for their breach.
On Law Day, it is worth recalling that in most of these disputes the State is not only the maker of the law but also a party to the dispute. The reforms suggested above ask no more of the State, as a litigant, than the discipline it expects of every private party.
*Advocate and Partner, Gandhi Law Associates.
1. (1974) 4 SCC 3 : 1974 SCC (L&S) 165.
2. (2021) 4 SCC 379 : (2021) 2 SCC (Civ) 555.
3. N.N. Global Mercantile (P) Ltd. v. Indo Unique Flame Ltd., (2023) 7 SCC 1.
4. Interplay Between Arbitration Agreements under Arbitration Act, 1996 & Stamp Act, 1899, In re, (2024) 6 SCC 1.
5. (2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204.
6. (2019) 15 SCC 131 : (2020) 2 SCC (Civ) 213.
7. Delhi Airport Metro Express (P) Ltd. v. DMRC Ltd. Ltd., (2022) 1 SCC 131 : (2022) 1 SCC (Civ) 330.
8. DMRC Ltd. v. Delhi Airport Metro Express (P) Ltd., (2024) 6 SCC 357 : (2024) 3 SCC (Civ) 112.
10. Kunal J. Vyas, “Delay and Litigation Cost: Major Roadblocks in Arbitration Process”, Bar and Bench, 22-5-2024, available at <https://www.barandbench.com/law-firms/view-point/delay-and-litigation-cost-major-roadblocks-in-arbitration-process>.
11. State of Bihar v. Bihar Rajya Bhumi Vikas Bank Samiti, (2018) 9 SCC 472 : (2018) 4 SCC (Civ) 387.
12. (2018) 6 SCC 287 : (2018) 3 SCC (Civ) 534.
13. (2020) 17 SCC 324 : (2021) 4 SCC (Civ) 373.
14. (1991) 1 SCC 212 : 1991 SCC (L&S) 742.
15. (2004) 3 SCC 553 : (2004) 118 Comp Cas 213.
19. (2025) 4 SCC 641 : 2024 SCC OnLine SC 3219 : (2025) 2 SCC (Civ) 1.
21. P.L. Adke v. Wardha Municipal Corpn., SLP (C) No. 4970 of 2021, pending before the Supreme Court.
22. (2020) 2 SCC 540 : (2020) 1 SCC (Civ) 614.
23. Om Construction Co. v. Ahmedabad Municipal Corpn., (2009) 2 SCC 486 : (2009) 1 SCC (Civ) 604.
24. Arbitration Petition No. 198 of 2024 (Guj).
25. M.P. Rural Road Development Authority v. L.G. Chaudhary Engineers & Contractors, (2012) 3 SCC 495 : (2012) 2 SCC (Civ) 210.
26. M.P. Rural Road Development Authority v. L.G. Chaudhary Engineers & Contractors (2018) 10 SCC 826 : (2019) 1 SCC (Civ) 97.
27. Kunal J. Vyas, “Reference of Disputes to Statutory Arbitration Tribunals: Aiding or Sabotaging the Cause of Arbitration in India?”, Bar and Bench, 7-3-2025, available at <https://www.barandbench.com/law-firms/view-point/reference-of-disputes-to-statutory-arbitration-tribunals-aiding-or-sabotaging-the-cause-of-arbitration-in-india>.
28. Gujarat Public Works Contracts Disputes Arbitration Tribunal Act, 19923, S. 3; Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983, Ss. 3 and 4.
29. (2017) 8 SCC 377 : (2017) 4 SCC (Civ) 72.
31. Central Organisation for Railway Electrification v. ECI SPIC SMO MCML (JV), (2025) 4 SCC 641 : 2024 SCC OnLine SC 3219 : (2025) 2 SCC (Civ) 1.
33. Shankaranarayana Construction Co. v. State of M.P., 2007 SCC OnLine MP 413, as noted in . , 2017 SCC OnLine MP 1448.
34. TRF Ltd. v. Energo Engg. Projects Ltd., (2017) 8 SCC 377 : (2017) 4 SCC (Civ) 72.
35. Perkins Eastman Architects DPC v. HSCC (India) Ltd., (2020) 20 SCC 760.
36. Central Organisation for Railway Electrification v. ECI SPIC SMO MCML (JV), (2025) 4 SCC 641 : 2024 SCC OnLine SC 3219 : (2025) 2 SCC (Civ) 1.
38. (2022) 9 SCC 593 : (2022) 4 SCC (Civ) 725.