Cyril Amarchand Mangaldas advises Nelnet Inc. on acquisition of 100% shareholding of Entab Infotech Pvt. Ltd. by NBS India Holding, LLC Married, earning and living separately: Can a daughter still claim compensation under S. 166 MV Act? Delhi HC answers Faculty of Law, University of Lucknow, organises departmental lecture on ‘An Introduction to Logic’ ICA–SCC Arbitration Institute Conclave on “Bridging India and the EU: Arbitration, Investment and the Future of Cross-Border Commerce” Fair market value of ESOP shares constitutes cost of acquisition under Section 49(2-AA) even if perquisite was taxed in UK, not India: ITAT Mumbai TOP LEGAL DEVELOPMENTS THIS WEEK [16-22nd Nov, 2026] | Bilkis Bano Case; ICJ Rohingya Genocide Judgment; Bakhra-Beas Power Dispute; and more

Competitive bidding process is to keep tariff low

By
Content reader

Listen to this article

Ready to read this article aloud.
Competitive bidding process is to keep tariff low

Gujarat High Court: The Bench comprising of R. Subhash Reddy, CJ and Vipul M. Pancholi, J, dismissed the letters patent appeal at the stage of admission as being devoid of merits, filed under Articles 226 and 227 of the Constitution, to issue writ of certiorari or other appropriate writ, to quash and set aside competitive bidding process, initiated by respondents, and also to stay the operation, implementation and execution of the order of Gujarat Electricity Regulatory Commission. Hence, it was challenged that in absence of final guidelines issued by Government, no bidding could be initiated for fixation of tariff, since it is contrary to policy notified by Ministry of Power.

The Court relying on Energy Watchdog v. Central Electricity Regulatory Commission, rejected the contention and held that in view of draft guidelines, competitive bidding process for fixation of tariff could be initiated since it will help to keep the tariff low, and the tariff decided by Commission will act as a ceiling tariff, and also held that where there are no guidelines framed, then the Commission’s power is not curtailed. The Court also observed that in case of any deviation between RFs, PPA, PSA and the final guidelines, the former would prevail, and in absence of the latter, provisional guidelines can be acted upon. [Indian Wind Energy Association v. Gujarat Urja Vikas Nigam Limited,  2017 SCC OnLine Guj 1335, decided on 14-11-2017]

WhatsApp LinkedIn

0 replies

Leave a Reply

Your email address will not be published. Required fields are marked *.

This site uses Akismet to reduce spam. Learn how your comment data is processed.