Case BriefsTribunals/Commissions/Regulatory Bodies

National Consumer Disputes Redressal Commission (NCDRC): V.K. Jain (Presiding Member), held that homebuyers cannot be made to wait indefinitely for the possession of the plots allotted to them and they are entitled to refund of the amount which they paid

Developer Company was selected by Government of Uttar Pradesh for the development of a township in Greater Noida in the name of ‘Sushant-Megapolis’.

No Time Frame

Large number of complainants booked residential plots and executed agreements with the OP. In the agreement, no time frame for delivering possession of the plots to the allottees was incorporated but the complainants were verbally told that the possession would be handed over within 36 months from the execution of the agreement.

Case of the Complainants

Complainants stated that the township has not been developed, hence no possession was offered to them along with other allottees.

Class Action

Therefore complainants approached the commission by way of class action under Section 12(1)(c) of the Consumer Protection Act seeking a refund of the amount paid by the allottees along with compensation.

Vide an order in 2017, Commission granted the permission to the complainants to institute this complaint on behalf of all the allotted who wanted a refund of the amount paid to the OP. Hence, public notice in two newspapers, circulated in Delhi/NCR were published and several allottees were permitted to join the complaint.

Preliminary objection raised by the OP was that the complaint is barred by limitation.

Analysis & Decision

OP having not completed the development and having not offered possession of the allotted plots to the allottees, they had a recurrent cause of action to file the Consumer Complaint, bench relied on the decision of Meerut Development Authority v. Mukesh Kumar Gupta, (2012) CPJ 12 (SC).

Commission found no merit in the above contention.

Farmers’ Protest | Compulsory Acquisition

With regard to delay in development due to the farmer’s protest, bench on perusal of the communication sent by OP noted that there was no dispute with the farmers as the land comprised in the project namely ‘Megapolis’ was concerned, the said land having been purchased by the complainant on market rate with the consent of landowners, the said case is not of compulsory acquisition of land by the State government.

Small Parcels of Land | Patches required to be acquired from State Government

The proposed project was a large land acquired directly from the farmers, though there were some small patches which were to be acquired from the State Government. OP having advertised the project and having executed the agreements for development and sale of plots, it was for them to purchase those small patches of land from the landowners at a negotiated price even if they had to pay a price higher than the price they were willing to pay.

Hence, it could not be said that the non-acquisition of such small parcels of land delayed the project.

Further, the bench stated that even if the plea taken by the OP with respect to non-acquisition of those small parcels of land is accepted on its face value, the allottees cannot be made to suffer for the inability of the OP to acquire those land parcels.

It’s been 12 years since the sale of the said plots started, but till this date, it is not known whether the OP will be able to complete the development work and if so when the said development would be completed.

Class Action

Counsel for the complainant stated that they have settled with eleven allottees other than the original complainants and they are in negotiations with thirteen other allottees.

For the above-stated, Commission stated that even if the above situation prevails, that would not lead to the dismissal of the class action. Once the jurisdiction of this Commission by way of a class action is invoked, the Commission is required to take the matter to its logical conclusion unless the matter is settled with each and every member of the class.

No Specific Time Period

Commission added to its analysis that though no specific time period for completing the development and offering possession to the allottees was indicated in the agreement, that would not entitle the builder to prolong the development work to an indefinite period.

As far as the development of plots is concerned, such a work does not require as much time as required for construction of group housing flats in multistoried buildings.

“…the development work of the plots, even on a large scale, must be completed within a period of three years from the approval of the lay-out plans.”

Bench relied on the Supreme Court decision of Pioneer Urband Land & Infrastructure Ltd. v. Govindan Raghavan, (2019) 5 SCC 725 and Kolkata West International City (P) Ltd. v. Devasis Rudra II, (2019) CPJ 29 (SC).

In view of the above discussion, Commission held that the allottees of residential plot in the project namely ‘Sushant Megapolis’ cannot be made to wait indefinitely for the possession of the plots allotted to them and they are entitled to refund of the amount which they paid to the OP along with appropriate compensation.

Further, the OP shall refund the entire principal amount received and pay Rs 50,000 as cost of litigation.[Bhrigu Kaushik v. Ansal Hi-Tech Township Ltd., Consumer Case No. 1951 of 2016, decided on 16-10-2020]

Case BriefsTribunals/Commissions/Regulatory Bodies

Securities and Exchange Board of India (SEBI): The Board comprising S.K. Mohanty whole time member, concluded that launching/ floating/ sponsoring / causing to sponsor any ‘collective investment scheme’ (CIS) by any person requires obtaining of a requisite certificate of registration from SEBI.

Maitreya Plotters and Structures Private Limited (MSPSL), a company engaged in the real estate business purchased large quantities of land in different States, divided it into smaller plots as per requirements of customers and then sold it. In the year 2013, it was found that MSPSL had illegally mobilized funds from the public through CIS without obtaining a certificate of registration from SEBI. 

The issue for determination was: whether mobilization of funds by MPSPL under its various schemes/plans for ‘purchase or booking of plots of land’ fell under the ambit of CIS in terms of Section 11AA of the SEBI Act, 1992. 

The Regulator noted that payments received from investors were pooled and utilized by MPSPL for its schemes. The property, that was part of its scheme, was managed by MSPSL on behalf of investors. An agreement entered into between investor and MPSPL vested it with the right to carry out development work on the plot, and investor was handed over the plot only after the said development was complete even if he had paid the entire consideration. Thus, investors were not aware of the plot allotted to them and did not have any control over utilization of funds for its development.

In view of the above, it was held that scheme offered by MPSPL was a CIS and required to be registered as mandated under Section 12(1B) of the Act.  MPSPL and its Directors were held jointly and severally liable to wind up its existing CIS and refund the contributions collected from investors with returns due to them and submit a report thereon to SEBI. [Maitreya Plotters and Structures (P) Ltd., In re,  WTM/SKM/EFD DRA1/06/2018-19, Order dated 31-01-2019]