Site icon SCC Times

[Amazon v. Future Retail] From Emergency Arbitrator to Group of Companies Doctrine – Delhi HC covers all while restraining Future Group from proceeding further with Disputed transaction

Delhi High Court: In the notable ruling of Amazon v. Future Retail, J.R. Midha, J. of Delhi High Court considered three crucial questions:

♦ What is the legal status of an Emergency Arbitrator?

♦ Whether the Emergency Arbitrator misapplied the Group of Companies doctrine which applies only to proceedings under Section 8 of the Arbitration and Conciliation Act?

♦ Whether the interim order of Emergency Arbitrator is Nullity?

Amazon.com invested Rs 1431 Crore in Future Coupons Private Limited (FCPL) based on certain special, material protective/negative rights available to FCPL in Future Retail Limited (FRL), namely, that the Retail Assets of FRL would not be alienated without the prior written consent of Amazon.com (Petitioner), and never to a Restricted Person. Further, an agreement was attained wherein it was stated FRL would be the sole vehicle for the conduct of FCPL and FRL’s conduct of business, resulting in benefit of the entire investment to FRL.

Within months of investment it was noted that the Biyanis which controls FRL breached the agreements by violating the contractual obligations, approved transaction relating to the transfer of its retail assets to Mukesh Dhirubhai Ambani Group (MDA) which is a Restricted Person as per Shareholders’ Agreement between petitioner and respondents (FCPL-SHA) [Disputed Transaction].

Timeline of Events:

05-10-2020
  • Arbitration Proceedings initiated.
  • Application filed to seek an ‘Emergency Interim Relief to restrain respondents from pursuing Disputed Transaction.
06-10-2020
  • Respondent 2 raised an objection with respect to Emergency Arbitrator’s jurisdiction.
09-10-2020
  • Petitioner requested for status quo to be maintained, however, respondents declined to give any assurance during the pendency of proceedings before the Emergency Arbitrator.
13-10-2020

Emergency Arbitrator called upon both the parties to submit their response pertaining to the following 4 Supreme Court Judgments:

Respondents raised objection to Emergency Arbitrator’s Jurisdiction.

16-10-2020 Arbitrator heard all the parties.
25-10-2020

Emergency Arbitrator passed an interim order and held that:

“the Emergency Arbitrator is an Arbitral Tribunal for all intents and purposes. The Emergency Arbitrator further noted that the Emergency Arbitrators are recognized under the Indian Arbitration framework.

Arbitrator observed that the petitioner made out a strong prima facie case that respondents were in breach of the contractual obligations. Further, the arbitrator added that the petitioner would suffer irreparable injury if the interim injunction was not granted.

Conclusion of Emergency Arbitrator

Petitioner has a strong prima facie case on the merits of the dispute, the petitioner’s rights under the FCPL-SHA, the SSA, and the FRL-SHA (insofar as it has been incorporated into the FCPL SHA) have been apparently compromised by the Respondents and the Respondents have given no good legal reasons for effecting the sale of FRL’s Retail Assets to the Restricted Person behind the petitioner’s back.

Point-Wise Analysis of the crucial questions raised in the present matter:

Legal Status

 Status of an Emergency Arbitrator is solely based on the party autonomy and the powers of such an arbitrator are similar to Arbitral Tribunal to decide an interim measure. Though Arbitral Tribunal is empowered to reconsider, modify, terminate or annul the order/award of the Emergency Arbitrator.

Emergency Arbitration is a very effective and expeditious mechanism to deal with the Emergency Interim Relief Application and has added a new dimension to the protection of the rights of the parties.

With this mechanism, a litigant gets justice within 15 days, though if the order of Emergency Arbitrator is not enforced, it would make the entire mechanism redundant.

In the present matter, by agreeing to incorporate the Rules of SIAC into the arbitration agreement, parties agreed to the provisions relating to Emergency Arbitration.

Current legal framework is sufficient to recognize the Emergency Arbitration and no amendment in this regard was required.

Section 2(1)(d) defines “arbitral tribunal” to mean a sole arbitrator or a panel of arbitrators, it is wide enough to include Emergency Arbitrator.

Under Section 17(1) of the Arbitration and Conciliation Act, the Arbitral Tribunal has the same powers to make interim order, as the Court has, and Section 17(2) makes such interim order enforceable in the same manner as if it was an order of the Court. The Interim Order is appealable under Section 37 of the Arbitration and Conciliation Act.

Whether Doctrine of Group of Companies applies only to proceedings under Section 8 of the Arbitration and Conciliation Act? 

Law relating to the Group of Companies doctrine is well settled by the Supreme Court in Chloro Controls India Private Limited v. Sever N Trent Water Purification Inc., (2013) 1 SCC 641, Cheran Properties Limited v. Kasturi and Sons Limited, (2018) 16 SCC 413 and MTNL v. Canara Bank, (2020) 12 SCC 767.

Group of Companies doctrine binds the non-signatory entity where the multiple agreements reflect a clear intention of the parties to bind both the signatory and non-signatory entities within the same Group.

 Supreme Court has laid down various tests for invoking the said doctrine.

Following are the Tests:

Bench also observed that the said doctrine has been very succinctly explained in the 4th Edition of Malhotra’s Commentary on the Law of Arbitration by Justice Indu Malhotra.

Here’s a Summary for a quick glance at the principles laid down by the Supreme Court on Group of Companies doctrine:

◊ The conduct of the parties reflect a clear intention of the parties to bind both the signatory as well as the non-signatory parties.

◊ The non-signatory company is a necessary party with reference to the common intention of the parties.

◊ The non-signatory entity of the group has been engaged in the negotiation or performance of the contract.

◊ The non-signatory entity of the group has made statements indicating its intention to be bound by the contract.

◊ A direct relationship between the signatory to the arbitration agreement and the non-signatory entity of the group; direct commonality of the subject-matter and composite nature of transaction between the parties.

◊ The performance of the agreement may not be feasible without the aid, execution and performance of the supplementary or ancillary agreement for achieving the common object.

◊ There is a tight group structure with strong organizational and financial links so as to constitute a single economic unit or a single economic reality.

◊ The funds of one company are used to financially support or restructure other members of the group.

◊ The composite reference of disputes of fresh parties would serve the ends of justice.

Bench in view of the above, decided that the Group of Companies Doctrine is applicable to the present case and respondent 2 is a proper party to the proceedings – Why? Lets’ read the reasons:

Whether the Interim Order is Nullity?

In Court’s opinion, respondent plea of Nullity is to mislead this Court.

Bench agreed with the Emergency Arbitrator that the protective rights do not amount to control of the petitioner over FRL and do not violate the law.

In the present matter, since the respondents were continuing to violate the agreement even after the Emergency Arbitrator’s decision, the petitioner approached this Court for enforcement of the interim order of the Emergency Arbitrator.

Respondents did not dispute the breach of the agreements either before the Emergency Arbitrator or before this Court.

High Court noted that the whole thrust of the respondents before this Court is that the petitioner is a trillion-dollar company and Rs 1430 crore invested by them in the present case is peanuts for them and they should forget about this money as it is worth zero today.

Bench also quoted the senior counsel for respondent 2 for the above-said observation:

“…What happens to his 1430 crores………that is worth zero today. FRL is zero. FCPL coupon business is gone. For this American behemoth, 1400 crore would be rounded off………..”

Before parting with this decision, High Court stated that Emergency Arbitrator, V.K. Rajah SC is a well-known jurist.

Conclusion

All the objections raised by the respondents were rejected with a cost of Rs 20,00,000 to be deposited by the respondents with the Prime Minister Relief Fund for being used for providing COVID vaccination to the Below Poverty Line (BPL) category – senior citizens of Delhi.

Since the respondents deliberately and willfully violated the interim order, hence they are liable for the consequences enumerated in Order XXXIX Rule 2A of the Code of Civil Procedure.[Amazon.Com NV Investment Holdings LLC v. Future Coupons (P) Ltd., 2021 SCC OnLine Del 1279, decided on 18-03-2021]

Exit mobile version